About IIMVisakhapatnam
- Government of Andhra Pradesh allotted 241.50 acre (including 80 feet road) land located at Gambheeram Village of Anandapuram Mandal to IIM Visakhapatnam.
- Construction of boundary wall for the site was completed.
- Site handed over by Andhra Pradesh State government to IIM Visakhapatnam on March 8,2018.
- DPR approved by GoI on September 17, 2018 with a total estimated cost of Rs.807.76 crore and Rs 445 crore for Phase-I.
- The institute has appointed M/s. Arcop Associates Pvt. Ltd as an Architect, NBCC (India) Ltd as a Project Management Consultant (PMC) and Shapoorji & Pallonji as a construction agency for the proposed Permanent Campus.
Campus Construction Progress - 11.01.2022
Campus Construction Progress - 01.01.2022
Campus Construction Progress - 15.12.2021
Campus Construction Progress - 30.11.2021
Campus Construction Progress - 15.11.2021
Campus Construction Progress - 30.10.2021
Campus Construction Progress - 14.10.2021
Campus Construction Progress - 29.09.2021
Campus Construction Progress - 07.09.2021
Campus Construction Progress - 23.08.2021
Campus Construction Progress - 09.08.2021
Campus Construction Progress - 30.07.2021
Campus Construction Progress - 15.07.2021
Campus Construction Progress - 30.06.2021
Campus Construction Progress - 20.06.2021
Campus Construction Progress - 05.06.2021
Campus Construction Progress - 20.05.2021
Campus Construction Progress-05.05.2021
Campus Construction Progress - 22.04.2021
Permanent Campus Site Visit by the Director - 18.03.2021
Campus Construction Progress - 06.04.2021
Campus Construction Progress - 17.03.2021
Campus Construction Progress - 03.03.2021
Campus Construction Progress - 19.02.2021
Campus Construction Progress-05.02.2021
Campus Construction Progress-08.01.2021